Caveat Lector: Although great care has been taken in the compilation of the information contained on this web site, the authors are not liable for the accuracy in terms of error or omission. The information on this web site is subject to change without notice and without obligation on the part of the authors. The authors shall not be liable for technical failures or for failures beyond their control. Some posts may contain authors' personal opinions and views and the authors do not represent any company, corporation or institution.

Monday, August 8, 2011

Factory Acceptance Test: Nantong Hyosung Transformer Co., Ltd. (Part 3)

We can only take pictures of the transformer for FAT but we are not allowed to take pictures of the five areas of EHV workshops (coiling area, insulation processing area, core processing area, active part assembly area, and final assembly area) including other products inside.
Below are some of the shots during testing of the power transformers:


measurement of load loss of the power transformer

Nantong Hyosung engineers give orientation about the on going testing of power transformer

Testing of power transformer winding resistance using a special test equipment

setting up for the temperature rise testing of power transformer

Partial Discharge test on Power transformer

Oil analysis and dissolved gas analysis at their laboratory

An engineer looking at the obtained test results displayed on the computer